PART A. PERFORMANCE IN GENERAL
1. Assignment
2. Changes
3. Compliance with Law
4. Confidentiality of Data and Information
5. Contract Acceptance, Integration and Modification
6. Definitions
7. Design Responsibility
8. Disputes
9. Export Control Compliance and Cooperation
10. Indemnity
11. Independent Contractor
12. Inspection and Acceptance
13. Insurance - Professional Liability
14. Interpretation
15. Invoices and Payment
16. Liens
17. No Advertising
18. Nonwaiver
19. Notices
20. Property Rights in the Contract Work
21. Remedies
22. Scope of Performance
23. Standard of Performance
24. Termination
25. Third Party Rights
26. Time of Performance
27. Warranty
PART B. PERFORMANCE AT BUYER'S FACILITIES
1. Clean-Up of Work Site
2. Environmental
3. Insurance
4. Safety
5. Security
6. Treatment at Buyer's Medical Facilities
7. Use of Buyer's Equipment

PART A. PERFORMANCE IN GENERAL

  1. ASSIGNMENT
    Neither this Contract nor the consideration due hereunder may be assigned by Construction Manager, in whole or in part, without Buyer's prior written consent.
    Back to top
  2. CHANGES
    1. Buyer may at any time, by written order, make changes to this Contract. If any such change causes an increase or decrease in the cost of, or the time required for, performance of this Contract, Buyer shall make an equitable adjustment in the Contract Price, the performance schedule, or both, and shall so modify this Contract. If Buyer changes the Contract performance date(s) such that Construction Manager is required to work overtime, Buyer shall pay therefor an amount equal only to Construction Manager's actual additional labor costs occasioned by such overtime.
    2. Buyer’s engineering and technical personnel may from time to time render assistance or give technical advice or discuss or exchange information with Construction Manager’s personnel concerning the Contract Work. Such actions, however, shall not be deemed to be a change under this Changes paragraph and shall not be the basis for any equitable adjustment. Only an authorized representative of Buyer’s Purchasing Department may change this Contract.
    3. Within twenty (20) days from the date of receipt of any written change order, Construction Manager shall submit to Buyer a detailed written estimate of the impact of the change on the Contract Price and the performance schedule. Upon receipt of this estimate, Buyer shall begin good faith negotiations with Construction Manager to determine an equitable adjustment to the Contract.
    4. The failure of the parties to agree to any equitable adjustment shall be dispute under the Disputes paragraph of this Contract. Nothing in this Changes paragraph, however, shall excuse Construction Manager from proceeding with diligent performance of this Contract as changed.
    Back to top
  3. COMPLIANCE WITH LAW
    Construction Manager shall, in the performance of this Contract, fully comply with all applicable federal, state and local laws, rules, regulations, orders, conventions, ordinances and standards that relate to the Contract Work. Construction Manager shall defend, indemnify and hold Buyer harmless from any and all claims and liabilities resulting from any failure to so comply.
    Back to top
  4. CONFIDENTIALITY OF DATA AND INFORMATION
    Information furnished by Buyer and identified by Buyer as "NASSCO Proprietary/Trade Secret Information" or otherwise identified as subject to restricted access or dissemination shall be and remain property of Buyer; shall not be duplicated, used or disclosed to third parties except for the purpose and to the extent necessary for the performance of this Contract; and upon completion of this Contract, shall be delivered to Buyer or destroyed by Construction Manager as Buyer specifies (including all copies). Construction Manager shall take all reasonable precautions to maintain in confidence all such information, including the imposition upon any person, firm, or corporation to whom disclosure of such information is made in the course of performance under this Contract of conditions relating to the confidential treatment thereof to the same effect as those imposed upon Construction Manager herein. The obligations imposed upon Construction Manager herein shall not apply to such information that is already known to Construction Manager, is lawfully obtained or obtainable by Construction Manager from another source, is or comes into the public domain other than as a result of breach of this Confidentiality of Data and Information paragraph.
    Back to top
  5. CONTRACT ACCEPTANCE, INTEGRATION AND MODIFICATION
    1. Construction Manager shall strictly perform this Contract. Acceptance of this Contract is expressly limited to the terms and conditions hereof and shall be made by executing the "acknowledgment copy" of the purchase order and returning the same to Buyer. If for any reason Construction Manager should fail to accept this Contract in writing, any performance by Construction Manager of any portion of this Contract shall constitute complete acceptance of this Contract. Any terms proposed in the acceptance of this Contract, which add to, vary from, or conflict with the terms and conditions of this Contract, are hereby objected to and shall be void.
    2. This Contract constitutes the entire agreement between the parties and supersedes all previous communications, representations or agreements, whether oral or written, between the parties. No terms other than those set forth herein or in the purchase order shall apply. Construction Manager represents that, in entering into this Contract, it does not rely on any previous oral or implied representation, inducement, or understanding of any kind.
    3. This Contract may be amended or modified only by a written instrument executed by authorized representatives of both Buyer and Construction Manager.
    Back to top
  6. DEFINITIONS
    1. "Buyer" means National Steel and Shipbuilding Company.
    2. "Construction" means the work of improvement (or other work) to be performed by the Construction Contractor in accordance with the Specifications.
    3. "Construction Contractor" means the individual or entity identified by Buyer to perform the Construction.
    4. "Construction Manager" means the individual or entity identified on the face of the purchase order by whom the Contract Work is to be performed.
    5. "Contract" means the purchase order, these Terms and Conditions, the Specifications, and any other documents incorporated by referenced by the purchase order.
    6. "Contract Price" means the total price to be paid by Buyer to Construction Manager for the proper performance of the Contract Work as set forth in this Contract.
    7. "Contract Work" means the construction management services, data and materials to be provided by Construction Manager under this Contract.
    8. "Specifications" means the technical specifications, plans, data, drawings, diagrams, schedules and any other documents that describe the Construction.
    Back to top
  7. DESIGN RESPONSIBILITY
    In reviewing Construction Contractor’s submittals, change proposals, value engineering proposals, in reviewing constructability, and in performing any other review involving the Specifications, Construction Manager does not undertake to perform any design work, nor does it accept responsibility for the Specifications.
    Back to top
  8. DISPUTES
    1. Any dispute between Buyer and Construction Manager in connection with or arising out of this Contract shall be resolved by means of the following procedures:
      1. The dispute initially shall be referred to each party’s senior executive with responsibility for this Contract, who shall negotiate in good faith to reach a resolution of the dispute.
      2. In the absence of a resolution being achieved within thirty (30) days after either Buyer or Construction Manager offers to conduct the negotiations in subparagraph (a)(i), above, either party may take appropriate action pursuant to subparagraph (b) hereof.
    2. Any dispute not resolved in accordance with subparagraph (a), above, may be resolved by any lawful means, including litigation, which shall be initiated by either party in a court of competent jurisdiction in San Diego County, California, and both parties consent to such exclusive jurisdiction and venue.
    3. In resolving any dispute under this Contract, the prevailing party shall be entitled to recover from the other party all reasonable attorney's fees and costs incurred.
    4. Until final resolution of any dispute hereunder, Construction Manager shall diligently proceed with the performance of this Contract as directed by Buyer.
    Back to top
  9. EXPORT CONTROL COMPLIANCE AND COOPERATION
    Construction Manager shall comply with the Export Administration Regulations (15 CFR 730—774) and the regulations issued by the Office of Foreign Assets Control (31 CFR Chapter V), all other applicable laws, regulations and orders that control the export of commercial and dual-use items and associated technology. In addition, Construction Manager shall inform Buyer in writing of the name and citizenship of each employee of Construction Manager and Construction Manager’s subcontractors at any tier who will participate in the performance of this Contract at Buyer’s facilities who is not a United States citizen or lawful permanent resident and the name and address of each subcontractor at any tier who will participate in such performance that is not organized under the laws of any state of the United States. Construction Manager shall cooperate fully with Buyer in applying for any export license or approval which may be required for any such employee or subcontractor and in justifying and documenting any license or approval exception. Construction Manager shall not permit any such employee or subcontractor to participate in the performance of this Contract over Buyer’s objection based on noncompliance with this Export Control Compliance and Cooperation paragraph.
    Back to top
  10. INDEMNITY
    Construction Manager shall defend, indemnify and save Buyer, its affiliated companies, and each of their directors, officers, agents and employees, free and harmless from and against all claims and liabilities of any nature, and all costs and expenses incurred in connection therewith (including, but not limited to, attorneys fees) for death or injury to persons (including, but not limited to, agents and employees of Construction Manager and its subcontractors) and for damage or loss of property arising directly or indirectly out of or in connection with the performance of this Contract, including, without limitation, claims and liabilities based in whole or in part on the negligence or other theory of liability of Construction Manager or Construction Manager’s subcontractors, and excluding only claims and liabilities based on Buyer’s sole negligence or willful misconduct.
    Back to top
  11. INDEPENDENT CONTRACTOR
    In performing the Contract Work, Construction Manager and its employees and subcontractors shall be an independent contractor to Buyer and shall not be an agent or employee of Buyer. Construction Manager shall be solely responsible for determining the means and methods of performing this Contract. Construction Manager assumes full responsibility for the payment of all compensation, expenses, and benefits (including, but not limited to, Workers' Compensation, medical, and other benefits) to its employees and for all state and federal income tax, unemployment insurance, social security, disability insurance, and other applicable withholdings.
    Back to top
  12. INSPECTION AND ACCEPTANCE
    The Contract Work, including any documents, materials, equipment, and facilities, shall at all times be available for inspection and testing by Buyer. Buyer's inspection or failure to inspect shall not relieve Construction Manager of any obligations or liability under this Contract, nor shall it constitute acceptance of the Contract Work. Construction Manager shall reperform or replace any nonconforming Contract Work at Construction Manager's expense within ten (10) days of Buyer's written notice of nonconformance. If Construction Manager has not reperformed or replaced such nonconforming Contract Work within the 10-day period, Buyer may reperform or replace such nonconforming Contract Work at Construction Manager's expense. The Contract Work shall be accepted when Buyer determines that it conforms to this Contract, and such acceptance shall be conclusive of conformance except for latent defects, fraud or gross negligence.
    Back to top
  13. INSURANCE - PROFESSIONAL LIABILITY
    If required on the face of the purchase order, Construction Manager shall keep and maintain in effect at its sole cost and expense professional liability (errors and omissions) coverage with minimum limits of liability of $1,000,000 per occurrence and $1,000,000 in the aggregate.
    Back to top
  14. INTERPRETATION
    This Contract shall be enforced and interpreted under California law without regard to which party drafted the Contract or to California's choice of law provisions. If any provision of this Contract is determined to be unenforceable, all other provisions shall remain in effect. This Contract shall not be varied, supplemented, qualified or interpreted by any prior course of dealing or usage of trade. Paragraph headings are for convenience only and shall not be used to interpret this Contract. In the event of any conflict or inconsistency between any provisions of this Contract, the following precedence shall be followed: the purchase order; these Terms and Conditions; the Specifications; any other document incorporated by reference by the purchase order.
    Back to top
  15. INVOICES AND PAYMENT
    1. Invoices shall include: the purchase order number; the invoice number; description of all Contract Work performed; the dates of performance; comprehensive, itemized prices; prior payments received; terms; and discounts. Unless otherwise provided, any cash discount period shall commence on the date of receipt of Construction Manager's invoice. Incorrect and incomplete invoices shall be returned for correction and shall delay the commencement of Buyer's obligation to pay for performance of Contract Work and any discount period until a corrected invoice is received by Buyer. Buyer shall pay Construction Manager only for the complete, proper and timely performance of the Contract Work, and Buyer shall have the right to withhold payment for any failure of Construction Manager to strictly comply with this Contract. No payment of any portion of the Contract Price shall constitute acceptance of the Contract Work.
    2. Buyer shall pay Construction Manager within thirty (30) days from receipt of a proper invoice by Buyer.
    Back to top
  16. LIENS
    1. Construction Manager waives any and all rights to any lien against Buyer by Construction Manager or Construction Manager’s subcontractors.
    2. Buyer shall have the right to withhold any payment until Construction Manager shall furnish current written releases and waivers of all rights to claim or file liens, properly executed by Construction Manager and its subcontractors. Construction Manager’s acceptance of full payment of the Contract Price shall constitute satisfaction in full and release of all claims or demands of Construction Manager and its subcontractors against Buyer arising out of or connected with this Contract. If Construction Manager fails or neglects to pay any admitted claims for labor or material, Buyer may pay such claims and deduct such payments from funds due Construction Manager hereunder or, if such claims be disputed, withhold sufficient funds to pay such claims until they are resolved. Construction Manager shall immediately discharge or cause to be discharged any lien or charge of any kind which at any time is filed against the property of Buyer with respect to, or arising from, the performance of the Contract Work. If any such lien or charge is not immediately discharged, Buyer may discharge or cause to be discharged such lien or charge at the expense of Construction Manager.
    Back to top
  17. NO ADVERTISING
    Construction Manager shall not, in any manner, advertise or publish the fact that Construction Manager has contracted to perform the Contract Work or use the service mark "NASSCO" in any advertising or promotional materials without Buyer’s express written consent.
    Back to top
  18. NONWAIVER
    Buyer's waiver of any provision of this Contract shall not constitute wavier of that provision in any later circumstances or waiver of any other Contract provision.
    Back to top
  19. NOTICES
    Unless expressly directed otherwise, notices required by this Contract to be given by Construction Manager or Buyer to the other party shall be personally served upon Construction Manager or Buyer or served by facsimile and first class mail addressed to the appropriate address hereinafter set forth or to such other address as Construction Manager and Buyer may hereafter designate by written notice. If served by facsimile and first class mail, service will be considered complete and binding on the party served immediately upon completion of said facsimile transmission, as evidenced by a confirmation of successful transmission.

      To Seller:
      As indicated on face of the purchase order

      To Buyer:
      National Steel and Shipbuilding Company
      P.O. Box 85278
      San Diego, CA 92186-5278
      Attn: Manager, MRO Purchasing
      Facsimile Number: (619) 544-3677
    Back to top
  20. PROPERTY RIGHTS IN THE CONTRACT WORK
    All data and materials prepared or developed by Construction Manager in connection with the performance of the Contract Work shall be Buyer's exclusive property and shall be provided to Buyer upon completion of performance of this Contract, upon termination of this Contract, or upon Buyer's earlier request.
    Back to top
  21. REMEDIES
    All remedies are cumulative, and the exercise of a remedy conferred by this Contract or in law or equity shall not preclude the exercise of any other remedy under this Contract or in law or equity.
    Back to top
  22. SCOPE OF PERFORMANCE
    Construction Manager shall supply and furnish at the location where the Contract Work is to be performed all labor, materials, equipment, tools, services, and supervision, and shall bear all items of expense, necessary for the complete and satisfactory performance of this Contract, except such items that Buyer, in this Contract, specifically agrees to supply or furnish to or for the use of Construction Manager. Any labor, materials, equipment, tools, services or supervision not specifically described in this Contract, but which may be fairly implied as required thereby or necessary to properly complete the Contract Work, shall be deemed within the scope of the Contract Work and shall be provided by Construction Manager at Construction Manager’s sole expense. Construction Manager shall act as Buyer’s agent in properly managing the Construction performed by the Construction Contractor.
    Back to top
  23. STANDARD OF PERFORMANCE
    1. Construction Manager shall perform the Contract Work using reasonable diligence, exercising its best judgment, and using the care and skill ordinarily used by reputable similar persons or entities in providing the same or similar services under similar circumstances. Construction Manager is on notice that Buyer is relying on the care, skill, diligence and judgment exercised by Construction Manager in performing the Contract Work. Construction Manager shall use its best efforts to ensure that the Construction Contractor performs properly and in accordance with the Specifications.
    2. Construction Manager shall be responsible to the Buyer for acts and omissions of the Construction Manager’s employees, subcontractors, and their agents and employees, and other persons, including engineers, and other design professionals, performing any portion of the Construction Manager’s obligations under this Contract.
    3. If Construction Manager subcontracts any portion of the Contract Work, Construction Manager shall provide Buyer with the name and address of such subcontractor prior to executing such subcontract. Buyer may decline the usage of such subcontractor based on Buyer’s independent evaluation of subcontractor’s qualifications.
    Back to top
  24. Termination
    1. For Convenience: Buyer may terminate this Contract for convenience at any time upon ten (10) days prior written notice. In the event of such termination for convenience, Buyer shall pay Construction Manager for Contract Work properly performed to the date of termination.
    2. For Default: Buyer may terminate this Contract for default if Construction Manager: fails to assure timely performance; fails to perform on time; ceases performance prior to completion of this Contract; evidences insolvency or financial inability to perform; or fails to cure the material breach of any other provision of this Contract within ten (10) days of notice of such breach.
    3. In the event Buyer terminates this Contract in whole or in part for default, Buyer may procure, upon such terms and in such manner as Buyer may reasonably determine, services similar to the Contract Work specified herein, and Construction Manager shall be liable to Buyer for any excess costs for such similar services. If this Contract is terminated only in part, Construction Manager shall continue the performance of this Contract to the extent not terminated.
    4. Upon termination of this Contract, either for convenience or for default, Construction Manager shall immediately cease performance of the Contract Work; shall immediately return to Buyer all information, materials and documents acquired from Buyer; and shall immediately provide to Buyer all information, materials and documents prepared or developed by Construction Manager in connection with performance of the Contract Work. Further, Construction Manager's obligations as set forth in the Property Rights in the Contract Work and the Confidentiality of Data and Information paragraphs herein shall survive any termination of this Contract.
    Back to top
  25. Third Party Rights
    This Contract is intended solely for the benefit of Buyer and Construction Manager and is not intended for the use or benefit of Construction Contractor or any other party. Nothing contained in this Contract is intended to make any person or entity that is not a signatory to this Contract a third party beneficiary of any right created by this Contract.
    Back to top
  26. Time of Performance
    1. Construction Manager shall perform the Contract Work in a diligent manner and in no event later than the time(s) specified on the face of the purchase order. Time of performance specified in this Contract is of the essence of this Contract. If at any time it reasonably appears to Buyer that Construction Manager is failing to make progress, such that performance may not be completed in accordance with this Contract, Construction Manager shall, within seven (7) days of a written request by Buyer, assure timely performance and represent to Buyer in writing Construction Manager’s best completion date. If the represented completion date is not within the original time for completion of performance of this Contract, Buyer may terminate this Contract for default in accordance with the Termination paragraph. Buyer shall further have the right, but not the duty, and without waiver of any other rights and remedies, which it may have, to extend the time for completion of performance. The new date for completion of performance shall be final, of the essence of this Contract, and subject to further change only in accordance with this Contract.
    2. Construction Manager shall not be liable for delays caused by force majeure events that are beyond the control and without the fault or negligence of Construction Manager, including, but not limited to, acts of God or the public enemy, fires, earthquakes, floods, epidemics, quarantine restrictions or natural disasters, on condition that Construction Manager notifies Buyer of any such force majeure events within five (5) days of the start of any such delays. Construction Manager shall cooperate with Buyer, and Construction Manager shall use its best efforts, to recover any such delays caused by any such force majeure events.
    Back to top
  27. Warranty
    Construction Manager expressly warrants for a period of one (1) year from acceptance by Buyer that all Contract Work shall conform to this Contract and be performed in a proper and workmanlike manner. If any nonconformities or defects are discovered in the Contract Work, which are not caused by Buyer, Construction Manager shall replace or reperform any nonconforming or defective Contract Work at Construction Manager's sole expense within ten (10) days of Buyer's written notice. If Construction Manager has not replaced or reperformed such nonconforming or defective Contract Work within the 10-day period, Buyer may replace or reperform such nonconforming or defective Contract Work at Construction Manager's expense.
    Back to top

PART B. PERFORMANCE AT BUYER'S FACILITIES

In the event that Construction Manager, its employees, agents and subcontractors (including delivery persons), enters any facility owned, leased or operated by Buyer (including Buyer’s shipyard at 28th Street and Harbor Drive, San Diego, California), Construction Manager shall comply with the following additional terms and conditions. Performance at Buyer’s facilities includes, but is not limited to, rework and guarantee work.

  1. CLEAN-UP OF WORK SITE
    During the performance of this Contract, and upon completion of the Contract Work or earlier termination of the Contract Work, Construction Manager shall remove all debris, garbage or other waste material, including excess materials, scrap and equipment used or generated by Construction Manager in performance of this Contract from Buyer's facilities. Construction Manager shall be liable for and shall pay to Buyer, upon demand, all costs of removal for materials or equipment not so removed.
    Back to top
  2. ENVIRONMENTAL
    Construction Manager shall comply with Buyer’s environmental policies and procedures and with all federal, state and local laws and regulations regarding the use and disposition of hazardous substances.
    Back to top
  3. INSURANCE
    1. Without prejudice to Buyer’s rights and Construction Manager’s obligations under the Indemnity paragraph herein, Construction Manager shall keep and maintain in effect at its sole cost and expense the following policies of insurance:
      1. Commercial General Liability insurance with coverage to include broad form property damage, personal injury, premises, completed operations, and products and contractual liability (specifically insuring the liability assumed under this Contract); and with a minimum bodily injury and property damage combined single limit of $2,000,000 per occurrence and $2,000,000 in the aggregate.
      2. Commercial Automobile Liability insurance with coverage to include owned, hired, and non-owned vehicles; and with a minimum bodily injury and property damage combined single limit of $2,000,000 per occurrence.
      3. Workers' Compensation and Longshore and Harbor Workers' Compensation Act insurance with limits conforming to the statutory requirements of the State of California and the United States of America, respectively.
      4. Jones Act coverage with minimum limits of liability of $2,000,000 per occurrence and $2,000,000 in the aggregate, if Construction Manager or its employees are assigned aboard a vessel for any reason and to any extent.
    2. Each such policy shall be underwritten by an insurance company satisfactory to Buyer; shall provide that it is primary insurance to, and noncontributing with, any other insurance carried by Buyer; and shall obligate the insurer to give Buyer not less than thirty (30) days prior written notice in the event of policy cancellation or any material change therein. Certificates evidencing such policies, in a form satisfactory to Buyer, shall be delivered to Buyer upon issuance of the purchase order, and renewals thereof shall be sent to Buyer at least ten (10) days prior to the expiration of the respective policy terms. The policies referred to above in subparagraphs (a)(1) and (a)(2) shall be endorsed to name Buyer as an "additional insured," and the certificates provided to Buyer shall reflect such endorsement. The policies referred to above in subparagraphs (a)(3) and (a)(4) shall contain a waiver of subrogation in favor of Buyer.
    3. Notices regarding insurance policies shall be provided in writing and shall be deemed delivered five (5) days after deposit in the U.S. Mail, postage prepaid, certified mail and return receipt requested, when addressed to National Steel and Shipbuilding Company, Attention: Risk Manager (M/S 20-E), P.O. Box 85278, San Diego CA 92186-5278.
    4. The insurance coverage limits stated above are minimum insurance coverage requirements, not limits of Construction Manager’s liability. Notwithstanding the above-required insurance policies, Construction Manager shall be obligated for the full and total amount of any damage, injury, expense or loss.
    Back to top
  4. SAFETY
    1. Construction Manager shall be solely responsible for the safe conduct of all persons employed by Construction Manager and its subcontractors. Construction Manager shall comply with all applicable federal, state, and local health, safety and fire protection laws and regulations. Construction Manager shall also comply with Buyer's safety policies and procedures. Any failure by Construction Manager or any of its suppliers to comply with any such safety policies, procedures, laws or regulations shall constitute a material breach of this Contract. Under no circumstance shall compliance with Buyer's safety policies and procedures alone be considered complete satisfaction of the requirements of this subparagraph.
    2. Construction Manager shall complete the following prior to commencement of performance of the Contract Work:
      1. Provide to Buyer's Safety Department the name, telephone number and title or position of the person who has the authority to correct any safety violations by Construction Manager during the performance of the Contract Work ("Construction Manager’s Safety Representative").
      2. Construction Manager's Safety Representative, together with equivalent representatives of Construction Manager’s subcontractors who are expected to perform at Buyer's facilities, shall meet with Buyer's Safety Manager or designee to review applicable safety policies and procedures.
      3. Provide to Buyer's Safety Department a copy of Construction Manager's written safety policies and procedures.
      4. Provide to Buyer's Safety Department a copy of all Material Safety Data Sheets ("MSDS") for all chemical compounds that Construction Manager anticipates using in performing the Contract Work at Buyer's facilities.
      5. Cause each of Construction Manager’s and subcontractor’s employees who will be in Buyer's facilities to complete a "Personal Protective Equipment" statement acknowledging their safety responsibilities.
    3. Construction Manager shall immediately notify Buyer's Safety Department, in writing, upon receiving notice of any inspection from either United States OSHA or California OSHA representatives of their work area at Buyer's facilities. In the event of such an inspection, Construction Manager shall permit Buyer's personnel to be present at any opening conference, the inspection, and any closing conference, and Construction Manager shall provide Buyer with copies of all correspondence, including citations, received from OSHA or Cal OSHA.
    4. If, in Buyer's sole opinion, Construction Manager fails to comply with this Safety paragraph, Buyer, may without prejudice to any other legal or contractual rights of Buyer, issue an order stopping all or part of the Contract Work. Construction Manager shall have no claim for extension of time or for compensation or damages by reason of or in connection with such work stoppage.
    5. Construction Manager shall remove from Buyer's facilities any of Construction Manager’s or Construction Manager’s subcontractor’s employees immediately upon Buyer's request based upon (in Buyer's sole opinion) violation of Buyer's safety policies or procedures or violation of applicable federal, state or local safety laws or regulations.
    Back to top
  5. SECURITY
    Construction Manager shall comply with Buyer's security policies and procedures regarding personnel administration, vehicle operations, and general security practices. Willful or repeated negligent noncompliance by Construction Manager or any of its subcontractors with any such security policies or procedures shall constitute a material breach of this Contract.
    Back to top
  6. TREATMENT AT BUYER'S FACILITIES
    Buyer shall have no obligation to furnish medical treatment to Construction Manager's employees while such employees may be working in Buyer's facilities. In the event Buyer's Medical Department furnishes medical treatment to any such employee, Construction Manager shall defend, indemnify and hold harmless Buyer, its affiliated companies, and the directors, officers and employees of each of them, from and against any and all claims, demands or causes of action, by Construction Manager's employees or their representatives, heirs or assigns for costs or damages (including without limitation punitive damages and reasonable attorney fees) arising out of or in connection with medical treatment furnished by Buyer, including claims based upon the negligence of Buyer, and excluding only claims based on Buyer’s sole negligence or willful misconduct.
    Back to top
  7. USE OF BUYER'S EQUIPMENT
    Construction Manager shall not use, or permit any third party to use, any of Buyer's equipment, tools, devices, apparatus or property ("Buyer's Equipment") without Buyer's express, written consent. If Buyer so consents, Construction Manager shall ensure that only qualified, properly trained persons use Buyer's Equipment and that such persons obey all of Buyer's applicable use procedures and requirements and all applicable federal, state and local laws and regulations. If Buyer so consents, Buyer's Equipment is provided "as-is," with no warranty, express or implied, as to its merchantability, fitness for any particular purpose, current condition, or prior maintenance history. Construction Manager is responsible for all risk of loss of or damage to Buyer's Equipment used by Construction Manager.
    Back to top

 